We stained the concrete floor of the basement this week. This is not a project for the faint of heart. Or lungs. If someone has health issues...especially respiratory problems, this is not the DIY project for you. In fact, I'd recommend a week-long vacation someplace far far away.
We decided we would do the labor, but we hired a pro to be the head of the project and lead us through the process. You only get one shot with this stuff. Once it's down, it's permanent. Greg gave us a list of chores to have completed prior to staining day, and a list of items to have on hand.
Ed had the surface sufficiently sanded and vacuumed, and we taped protective paper along the painted walls. Greg put the acid stain in a plastic sprayer. As he sprayed, we scrubbed it in with plastic scrub brushes attached to pushbroom handles.
This stain is acid based. It uses muratic acid which reacts to the calcium and lime in the concrete to etch the color into the surface. This, like many chemical reactions, causes very nasty fumes to accumulate rather quickly. There are no windows in the basement, only a roll up door at the other end of the building. By the time we got finished spraying and scrubbing the gym area, we were coughing and sucking air. We took a break, located several box fans and shouldered on. Once you start, you can't stop until it's done.
By afternoon we had the whole basement (except the woodpile room) stained. The chemical process takes several hours, so we waited until the next morning to apply the neutralizing solution.
That was a good thing because it took that long to clear our lungs and start feeling normal. I was a little concerned about the neutralizing process because it requires a mixture of household ammonia and water, applied liberally, then mopped up, in several applications. Was this going to cause a repeat of yesterday's gasping and coughing? I was pleasantly surprised. It was a bit of an aerobic workout however. We mopped the whole thing with big heavy cotton string mops, over and over. After the last rinse, Ed had the room heaters, several fans, and two dehumidifiers running for several days to thoroughly dry the floor.
Yesterday, Greg returned to start sealing the finish. The sealer went into a new plastic garden sprayer,was misted on the floor, then mopped in with a new microfiber string mop. That way there aren't little pieces of cotton lint permanently left in the finish. Two coats of the first sealer, five coats of the second sealer..sprayed and mopped.
We've ordered the high-solids wax which finished the project. It should be here mid-week. That will be five more coats mopped in, then burnished for hardness. So far, we're really happy with the end result..and that we lived through the process.
Glorious!
-
The geode sidelight was installed last month. A special shout out to my
husband for the installation. I did get the hint however that he would
rather no...
8 years ago
No comments:
Post a Comment